The most common contract structure for Melbourne commercial fitouts. The builder agrees to complete a defined scope of works for a fixed total price — the…

Fitout Contract Guide Melbourne | What to Include & Watch For

Contract Price Structures

Fixed Lump Sum (Fixed Price Contract)

The most common contract structure for Melbourne commercial fitouts. The builder agrees to complete a defined scope of works for a fixed total price — the client knows from the outset what the fitout will cost.

How it works:

  • The builder prices the full scope of works (documented in drawings, specifications, and schedules)
  • A single fixed price is agreed
  • The builder carries the risk of labour, material, and overhead cost variations within the agreed scope
  • If the project is completed for less than the contract price, the saving belongs to the builder
  • If the project costs more (due to scope creep, unforeseen conditions, or builder underpricing), the builder bears the additional cost (subject to the variation provisions)

Advantages for the client:

  • Price certainty — the client knows the budget commitment before work starts
  • Risk transfer — the builder bears cost risk within the agreed scope
  • Simple to administer — progress claims against a fixed price are straightforward

Disadvantages:

  • Requires a complete and documented scope to price accurately — if the scope is incomplete or ambiguous at the time of pricing, the fixed price is less reliable
  • Builder prices in a risk margin — fixed price contracts typically include a contingency built into the builder's price
  • Variations (scope changes) are priced at the builder's discretion and can become a source of dispute

Best for: Fitouts with a well-defined, fully documented scope and a fixed programme.

Cost-Plus (Reimbursable) Contract

The builder is reimbursed for actual costs incurred (labour, materials, subcontractors) plus a fee (either a fixed fee or a percentage of costs).

How it works:

  • Client pays: actual labour costs + actual material costs + actual subcontractor costs + builder's fee (typically 10–20% of costs)
  • No fixed price — the final cost is determined by the actual costs incurred
  • Client carries the cost risk — if the project costs more than estimated, the client pays more

Advantages:

  • Appropriate where the scope cannot be fully defined at the outset (heritage buildings, complex upgrades to occupied premises, discovery-dependent works)
  • Transparent — the client sees the actual costs
  • Builder has no incentive to cut corners on materials or labour (since costs are reimbursed)

Disadvantages:

  • No cost certainty — the final price is unknown at contract execution
  • Client carries all cost risk
  • Requires active cost monitoring by the client or a client-side quantity surveyor
  • Builder's fee is a percentage of costs creates a perverse incentive — the more the project costs, the higher the builder's fee

Best for: Highly complex or incomplete-scope projects where a fixed price cannot be established; heritage or unusual buildings where significant unknowns exist.

Guaranteed Maximum Price (GMP)

A hybrid contract structure — the builder provides a cost-plus arrangement with a guaranteed upper limit on the total cost.

How it works:

  • Works are priced on a cost-plus basis (actual costs + fee)
  • A Guaranteed Maximum Price (GMP) caps the total cost the client will pay
  • If actual costs exceed the GMP, the additional cost is borne by the builder
  • If actual costs are below the GMP, the saving may be shared between the client and builder (at a pre-agreed ratio) or kept entirely by the client depending on the contract

Advantages:

  • Provides a cost ceiling (client's maximum exposure is capped)
  • Cost-plus transparency below the GMP
  • Builder has some incentive to control costs (risks cost overrun above the GMP)

Disadvantages:

  • More complex to administer than a simple fixed price
  • Builder typically sets the GMP conservatively — the GMP will be higher than a competitive fixed price tender
  • Requires careful scope documentation to establish what is and is not included in the GMP

Best for: Projects with a mostly-defined scope but where some unknowns remain; larger projects where the client wants cost transparency with a ceiling.

Key Contract Terms to Understand

Scope of Works

The scope of works defines exactly what the builder is obligated to construct. In a fixed price contract, anything not in the scope is a variation (additional cost). A well-drafted scope includes:

  • Architectural drawings and reflected ceiling plans
  • Joinery drawings and specifications
  • Mechanical, electrical, hydraulic, and fire services schedules
  • Finishes schedules (floor finishes, paint colours, benchtop materials, etc.)
  • Exclusions list (items specifically noted as not in scope)

Key risk: Scope gaps. If the drawings are incomplete, the builder may price only what is documented and then issue variations for items that the client assumed were included. Request a comprehensive exclusions list and ensure all expected finishes and systems are included in the documented scope.

Programme and Practical Completion Date

The programme specifies:

  • The commencement date (when the builder gains access to the site)
  • The practical completion date (when the fitout is to be delivered)
  • Milestone dates (if applicable — e.g., completion of slab works, fitout of specific zones)

Liquidated damages: Most commercial fitout contracts include a liquidated damages clause — if the builder fails to achieve practical completion by the agreed date, the builder pays the client a specified daily amount (liquidated damages) for each day of delay. Liquidated damages are a pre-agreed estimate of the client's loss from delay — typically $500–$3,000/day for a medium commercial fitout. They must be a genuine pre-estimate of loss, not a penalty.

Extension of time: The contract will specify grounds on which the builder is entitled to an extension of time (and corresponding extension of the practical completion date) — typically including client-instructed variations, client delays, and specified force majeure events. The builder must issue a formal extension of time claim within a specified timeframe.

Variations

A variation is any change to the agreed scope of works — an addition, deletion, or modification. In a fixed price contract, every variation changes the contract price.

Key terms:

  • Instruction to vary: The client (or superintendent) must formally instruct a variation — verbal instructions are dangerous and frequently disputed
  • Pricing of variations: Most contracts require the builder to provide a variation price before the work is carried out (or as soon as practicable); the client approves the price before the variation proceeds
  • Daywork: For variations where a fixed price cannot be established in advance (exploration works, demolition of unknown existing conditions), variation costs are recorded as time and materials at agreed daywork rates
  • Scope creep: The single most common cause of budget overrun in fitout projects is cumulative variations — individually small scope changes that add up to a significant cost increase. Track all approved variations against the original budget.

Progress Claims and Payment

Most fitout contracts use progress payments — the builder issues a progress claim (invoice) at agreed intervals (typically monthly or at agreed milestones), and the client pays within a specified timeframe.

Victorian Building and Construction Industry Security of Payment Act 2002 (BACISOPA): This Act provides statutory rights for contractors to receive timely payment. Under BACISOPA:

  • A claimant (builder) can serve a payment claim on any reference date (specified in the contract or monthly)
  • The respondent (client) must serve a payment schedule within 10 business days of receiving a payment claim, specifying the amount the client proposes to pay
  • If no payment schedule is provided, the full amount of the payment claim becomes due
  • Disputed amounts must be referred to adjudication (a fast-track dispute resolution process)

Retention: As discussed in the defects and warranty guide, most contracts withhold a percentage (typically 5%) of each progress claim as retention security. Half is released at practical completion; the remaining half at final completion (end of DLP).

Superintendent

Many commercial fitout contracts appoint a superintendent — typically the architect, interior designer, or project manager — to administer the contract on behalf of the client. The superintendent:

  • Issues instructions and approves variations
  • Certifies progress payments
  • Assesses the builder's claims for extension of time
  • Issues the Certificate of Practical Completion

The superintendent must act independently and honestly when certifying — they owe duties to both the client and the builder. They are not the client's advocate; they are the contract administrator.

Dispute Resolution

Standard form contracts (AS 4902, AS 4000) include a stepped dispute resolution process:

  1. Negotiation between the parties
  2. Mediation or expert determination
  3. Arbitration or litigation

The Security of Payment Act provides a faster route for payment disputes — adjudication can produce a binding determination within 10 business days.

Standard Form Contracts

AS 4902–2000 (Design and Construct): Standard form for design-and-construct projects where the builder is responsible for both design and construction. Most commonly used for larger or more complex fitout projects.

AS 4000–1997 (General Conditions of Contract): Standard form for construct-only projects where the client provides the design. Less common for fitouts (most Melbourne fitouts are design-and-construct or have the builder managing design subcontractors).

MBA / HIA forms: Master Builders Association and Housing Industry Association contract forms — used by many smaller commercial fitout contractors.

Bespoke builder contracts: Many larger fitout builders use their own contract forms. Review these carefully — bespoke contracts typically favour the issuing party. Key areas to scrutinise: variation pricing, extension of time provisions, liquidated damages, and defect liability.

Key Questions Before Signing

  1. Is the scope of works complete and fully documented? Are there any exclusions that surprise you?
  2. What is the mechanism for variation pricing — will you know the cost before work proceeds?
  3. What are the liquidated damages provisions — what daily rate applies for late completion?
  4. What are the progress payment intervals and payment timeframes?
  5. What is the retention amount and when is each tranche released?
  6. Who is the superintendent and what are their authorities?
  7. What insurance does the builder hold (contract works, public liability, professional indemnity)?
  8. What is the Defect Liability Period and what retention is held?

Frequently Asked Questions

Should I use a fixed price or cost-plus contract for my fitout?

For most Melbourne commercial fitouts with a well-documented scope, a fixed price contract provides better budget certainty and appropriate risk allocation. Cost-plus is appropriate where the scope is genuinely incomplete or where significant unknowns exist (heritage buildings, working in occupied premises, complex existing conditions). If you are uncertain about your scope, invest in completing the design documentation before entering a fixed price contract — an incomplete scope produces an unreliable price.

What is the Security of Payment Act and how does it affect me as a fitout client?

The Building and Construction Industry Security of Payment Act 2002 (Vic) gives contractors the right to serve payment claims and receive payment (or a payment schedule) within 10 business days. If you receive a BACISOPA payment claim and do not respond with a payment schedule within 10 business days, the full claimed amount becomes a debt. Always respond to payment claims within the statutory timeframe — even if you dispute the amount.

Can I make changes to a fitout while it is under construction?

Yes — but each change is a variation that adjusts the contract price and may affect the programme. Accumulating small variations (scope creep) is one of the most common causes of budget overrun. Establish a variation control process: no variation proceeds without a written instruction; no variation instruction is issued without a price approval. Track all variations against the original budget.

Spacez uses clear, client-friendly contract documentation on all Melbourne commercial fitout projects — fixed price, fully specified, with transparent variation pricing. Contact us to discuss your project.