Spacez insight · April 2026 · 7 min read
Fitout Handover & Commissioning Melbourne | What to Expect
Practical completion is the contractual milestone at which the fitout works are sufficiently complete for their intended purpose — the fitout is functional…
Practical Completion — What It Means
Practical completion is the contractual milestone at which the fitout works are sufficiently complete for their intended purpose — the fitout is functional, all major systems are operational, and the space is ready for occupation — even if minor defects (items on the defects list) remain outstanding.
Practical completion is not the same as:
- Total completion: Practical completion allows for outstanding minor defects; total or final completion requires all defects rectified
- Perfection: Some minor cosmetic defects at practical completion are normal; the defects list captures these for rectification during the Defect Liability Period
Who determines practical completion?
In standard commercial fitout contracts (AS 4902, AS 4000, or bespoke contracts), the builder issues a Notice of Practical Completion (NOPC) when they consider the works are practically complete. The superintendent (or the client's representative) assesses the notice and either:
- Issues a Certificate of Practical Completion (accepting that practical completion has been reached), or
- Rejects the notice with a written statement of reasons (identifying the works that must be completed before practical completion is reached)
Disputes about whether practical completion has been achieved are common — a clear contract definition and a thorough inspection process reduces the risk.
The Defects List (Snagging List)
The defects list (sometimes called the snagging list) is a written record of all items that do not comply with the contract specifications or that are incomplete at practical completion. It is one of the most important documents produced during the project.
Conducting the Practical Completion Inspection
A practical completion inspection should be conducted jointly — the builder, the client (or client representative), and (ideally) the project designer/interior designer walk through the entire fitout room by room. Allow at least 2–4 hours for a thorough inspection of a medium-sized fitout (300–800 sqm).
What to inspect systematically:
Joinery:
- All doors hang true, swing freely, and latch correctly (test every door)
- All drawers open and close smoothly on both sides (test every drawer)
- All cupboard hinges are adjusted (no dropped doors)
- Benchtop joints are flush and tightly sealed
- Silicone joints are continuous, neat, and not cracked
- All joinery hardware (handles, locks, hinges) is installed and functional
Plasterboard and paint:
- No visible nail/screw pops or joins telegraphing through the paint finish
- Paint is consistent in coverage, sheen, and colour
- Cornices and skirting are tightly joined and painted
- No paint runs, drips, or missed areas
Flooring:
- Carpet laid flat, seams not visible from standing height, no bubbles or ridges
- Tile lippage (adjacent tiles not flush) — walk the floor slowly
- Grout lines complete, consistent, and grouted to the edges
- LVP or timber flooring laid without gaps, with transitions neat at doorways
Mechanical (HVAC):
- All HVAC units turn on and operate
- Air diffusers balanced — test each zone is receiving conditioned air at appropriate volume
- Temperature control operates correctly
- No unusual noises from any unit
Electrical:
- All light fittings illuminate (walk the space with lights off first)
- Switches operate correctly for each circuit
- Dimmer switches function smoothly across the range
- All GPOs have power (use a plug-in tester)
- Data outlets are terminated and labelled
- Emergency lighting illuminates when tested
Wet areas:
- All taps and fixtures operate without leaks
- Drainage flows freely (run water to test)
- No grout voids, tile chips, or silicone gaps in wet areas
- Waterproofing test (for shower floors, shower walls to appropriate height)
General:
- All walls clean (no marks, pencil lines, or adhesive residue from construction)
- All glass (partitions, windows) clean and free from scratches
- All ceilings clean
- All plant rooms, risers, and back-of-house areas left clean
Documenting the List
Each defect must be documented with:
- Location (room/zone number or name)
- Description of the defect
- Photograph
A numbered list with corresponding photographs is the standard format. The list is agreed between the builder and the client's representative, signed, and forms part of the contract record.
Commissioning — Mechanical and Electrical Systems
Commissioning is the process of verifying that the building systems (HVAC, electrical, BMS/building management system, fire services) have been installed correctly and perform to specification. Commissioning is more than just switching systems on — it involves measurement, adjustment, and documentation.
HVAC Commissioning
HVAC commissioning involves:
- Air balance: Measuring and adjusting the air volume delivered to each supply diffuser and exhaust grille to match the design intent; typically performed by the HVAC contractor using a flow hood and calibrated instruments
- Temperature testing: Confirming that each zone can achieve and maintain the specified temperature range in representative conditions
- Controls testing: Verifying that thermostats, occupancy sensors, CO₂ sensors, and building management system controls operate as specified
- Noise testing: Confirming that fan units, ductwork, and diffusers operate within the specified noise levels (NRC in occupied areas)
A commissioning report is produced by the HVAC contractor, documenting measured vs specified air flows for each diffuser, temperature test results, and any adjustments made. This report should be handed over to the client at practical completion.
Electrical Commissioning
- All circuits tested and labelled on the distribution board
- Emergency and exit lighting tested (AS 2293 compliance testing)
- Safety switch (RCD) testing
- Data network tested (patch leads, port-to-port continuity, Wi-Fi coverage mapping where relevant)
- Access control and security systems tested (if in scope)
- Lighting control system (DALI, C-Bus, Lutron) programmed and tested
Fire Services
If the fitout includes any new or modified fire services (sprinklers, smoke detectors, exit signs, PA/intercoms):
- A fire services commissioning certificate from a licensed fire protection contractor is required
- The sprinkler system must be hydraulically tested after installation
- Smoke detectors must be tested for sensitivity
- Exit sign illumination must be tested
Occupancy Certificate and Building Permits
Certificate of Occupancy / Certificate of Final Inspection
When a building permit has been issued for the fitout, the relevant registered building surveyor (RBS) must issue either:
- Occupancy Permit: Required where the NCC classification changes (e.g., from warehouse to office, or from standard commercial to healthcare) — confirms the building complies with the NCC for the new classification
- Certificate of Final Inspection: For fitout works where the building classification does not change — confirms the works have been completed in accordance with the building permit
The client cannot legally occupy the premises (or allow occupation) until the occupancy permit or certificate of final inspection has been issued.
Important: The issuance of an occupancy permit or certificate of final inspection does not mean all contract defects have been resolved — it means the building surveyor has inspected the works and is satisfied they comply with the NCC. Defect items that don't affect NCC compliance (minor cosmetic items, non-critical joinery issues) may still be on the defects list.
Handover Documentation Package
The fitout builder should hand over a documentation package at practical completion. This package is essential for the ongoing management of the tenancy and must be archived:
| Document | Issued By | Purpose |
|---|---|---|
| Certificate of Practical Completion | Builder/Superintendent | Contractual milestone record |
| Defects list (agreed) | Builder + Client | DLP rectification record |
| As-built drawings | Builder/Designer | Record of what was actually constructed |
| HVAC commissioning report | HVAC contractor | Air balance, temp test results |
| Electrical test certificates | Electrical contractor | Compliance with AS/NZS 3000 |
| Fire services commissioning certificate | Fire contractor | AS 1851 compliance |
| Occupancy Permit / Certificate of Final Inspection | RBS | NCC compliance |
| Operations and Maintenance (O&M) manuals | Builder | Equipment maintenance requirements |
| Warranties and manufacturer guarantees | Builder | Product warranty documentation |
| Keys, access cards, and security codes | Builder | Physical handover of access |
O&M manuals are particularly important for complex systems (HVAC, electrical, security, AV). They contain the manufacturer's maintenance schedules, recommended service intervals, and contact details for service agents. Without O&M documentation, the client may void equipment warranties through incorrect maintenance.
Keys and Physical Handover
The physical handover includes:
- All keys (including master key, zone keys, individual door keys)
- Access card stock and programming instructions (for electronic access control)
- Security system codes and installer code
- Alarm monitoring account details
- Building management access credentials (if applicable)
Ensure the number of each key type matches the contract specification, and that lock cylinders are keyed as specified (separate zones, master keyed to a specified system).
Frequently Asked Questions
What is the difference between practical completion and final completion?
Practical completion is reached when the works are substantially complete and ready for occupation — minor defects may remain on the agreed defects list. Final completion (or total completion) is reached when all defects on the list have been rectified and the builder's obligations under the Defect Liability Period are fulfilled. The retention money (typically 5% of the contract sum) is released at final completion.
Can I occupy the fitout before the occupancy permit is issued?
No — occupying a commercial premises without the required occupancy permit is illegal under the Building Act 1993 (Vic). The building permit process and occupancy permit/certificate of final inspection must be completed before occupation.
What should I do if I find defects after moving in?
Document them in writing immediately — photograph and describe each defect — and notify the builder in writing. All defects notified within the Defect Liability Period (typically 12 months from practical completion) are the builder's obligation to rectify at no cost. Keep a running register of notified defects with dates and builder response records.
Spacez provides a comprehensive handover documentation package as standard on all Melbourne commercial fitout projects — including commissioning reports, as-built drawings, O&M manuals, and all regulatory certificates. Contact us to discuss your project.