Spacez insight · April 2026 · 7 min read

Fitout Project Management Melbourne | Timeline & Process Guide

In a design-and-build or traditional commercial fitout, the fitout builder is the principal contractor — they are legally responsible for the construction…

Fitout Project Management Melbourne | Timeline & Process Guide

Who Manages a Commercial Fitout?

The Fitout Builder as Principal Contractor

In a design-and-build or traditional commercial fitout, the fitout builder is the principal contractor — they are legally responsible for the construction phase of the project. This means:

  • All subcontractors (electricians, plumbers, mechanical trades, plasterers, tilers, glaziers, signage) are contracted to the fitout builder, not to you
  • The fitout builder manages the construction programme, trade sequencing, and site safety
  • The fitout builder is your single point of contact for all construction matters
  • The fitout builder is responsible for the quality of all subcontractor work

You should not be managing trades directly. If a builder asks you to coordinate subcontractors, manage material deliveries, or resolve trade disputes, that is a sign of poor project management — not normal practice.

The Fitout Builder as Project Manager — Pre-Construction

Before construction begins, a full-service fitout builder should also manage:

  • Design coordination — architects, interior designers, structural engineers, acoustic consultants, hydraulic engineers
  • Authority approvals — building permit applications, landlord consent submissions, planning permit applications (via specialist consultants)
  • Long-lead procurement — joinery fabrication orders, imported furniture, specialist equipment
  • Building management coordination — site induction, loading dock, after-hours access arrangements

Your Role as Client

You are responsible for:

  • Timely decision-making — approving designs, selecting materials, approving variations; delays in client decisions delay the programme
  • IT and technology procurement — engaging your IT team or contractor for structured cabling, server infrastructure, Wi-Fi, and AV systems (unless fully subcontracted to the builder)
  • Furniture procurement — if you are procuring furniture independently, managing the lead times and delivery coordination
  • Lease and legal — managing the landlord relationship, reviewing and approving consent packages, managing your solicitor
  • Staff communication — preparing staff for the occupation transition, briefing on new workplace protocols

The Fitout Programme — Stage by Stage

A well-managed fitout programme has seven stages, each with clear milestones.

Stage 1: Design (Weeks 1–6)

Key activities:

  • Site inspection and base building documentation review
  • Space planning — confirm layout, headcount, adjacencies
  • Concept design — materials, palette, joinery concept
  • Detailed design — architectural drawings, joinery drawings, services coordination
  • Structural engineering (if required — mezzanines, structural modifications)
  • Acoustic consulting (for complex fitouts)

Key milestones:

  • Space plan sign-off (Week 2)
  • Concept design sign-off (Week 3–4)
  • Detailed design issued for approvals (Week 5–6)

Client's critical path: Prompt review and sign-off on each design stage. A client who takes 2 weeks to review a space plan instead of 3–5 business days delays every subsequent stage.

Stage 2: Authority Approvals (Weeks 5–12, parallel with Stage 3)

Parallel streams:

Building permit (Weeks 5–9):

  • Appoint private building surveyor
  • Lodge building permit application
  • Respond to any RFI from surveyor
  • Receive permit

Landlord consent (Weeks 5–10):

  • Prepare consent package (drawings, specification, builder's details, insurance)
  • Submit to landlord/property manager (and separately to centre management for shopping centres)
  • Respond to conditions and queries
  • Receive written consent

Planning permit (if required, Weeks 1–16+):

  • Engage planning consultant (and heritage architect if HO applies)
  • Pre-application meeting with council (recommended)
  • Lodge application
  • Council assessment and any referrals
  • Receive permit

Client's critical path: Prompt review and approval of the consent package; prompt instructions on any landlord conditions.

Stage 3: Procurement and Fabrication (Weeks 5–13, parallel with Stage 2)

Key activities:

  • Joinery fabrication order placed (critical path item — typically 5–8 weeks)
  • Subcontractor engagement and scheduling
  • Long-lead materials ordered (imported tiles, specialist lighting, custom hardware)
  • Furniture orders placed (10–16 weeks for imported or custom furniture)
  • AV and technology equipment ordered

Key milestones:

  • Joinery fabrication commenced (Week 5–6)
  • All subcontractors engaged and scheduled (Week 8)
  • Long-lead materials confirmed and on order (Week 6–7)

Client's critical path: Final selection of all materials, finishes, and furniture before procurement close. Changes after procurement is committed generate variations (time and cost).

Stage 4: Construction (Weeks 11–20)

Typical construction sequence for a commercial office fitout:

WeekKey Works
1Demolition (if required), strip-out
1–2Structural works (if any)
2–4Wall framing, ceiling framing
3–5Electrical rough-in (conduit, cable, switchboard)
3–5Plumbing rough-in (supply, waste)
3–5Mechanical rough-in (ductwork, FCU installation)
3–5Fire services modifications
4–6Plasterboard lining, stopping, and jointing
5–7Tiling (floors and walls)
5–7Suspended ceiling grid and tile
6–8Joinery delivery and installation
7–9Electrical fit-off (power outlets, light fittings, switches)
7–9Plumbing fit-off (taps, basins, toilets)
7–9Mechanical commissioning (HVAC balance and test)
8–10Carpet/vinyl/flooring installation
8–10Painting (second coat and detail)
9–10Glazing (partition glazing, shopfront)
10Signage installation
10Final clean and snagging

Client's critical path: Attend weekly site meetings; make variation decisions promptly; keep IT contractor coordinated with the construction programme.

Stage 5: IT and AV Fitout (Weeks 9–12)

IT and AV fitout runs partially in parallel with the construction phase:

  • Structured cabling (data and phone) — installed after wall framing, before plasterboard lining; data cabling cannot be installed after plasterboard without breaking walls
  • Wi-Fi access points — mounted and cabled before ceiling tile installation
  • AV rack and meeting room equipment — installed in the fit-off phase (Weeks 8–10)
  • Testing and commissioning — all IT and AV tested before occupation

The most common IT mistake: Leaving the IT contractor engagement too late; arriving after the walls are lined and having to run surface conduit or cable through finished walls.

Stage 6: Practical Completion (Week 13+)

Key activities:

  • Builder's defects inspection and rectification
  • Client practical completion walkthrough
  • Defects list documentation
  • Certificate of Occupancy from PBS
  • As-built drawings issued
  • Warranties and compliance documentation issued

Key milestones:

  • Defects list agreed
  • Certificate of Occupancy received
  • Keys handed over

Stage 7: Post-Occupation (Months 1–12)

  • HVAC commissioning check (after first summer and winter)
  • Defects liability period — builder rectifies notified defects at no charge
  • Staff feedback on workplace performance (acoustic, thermal, lighting)
  • Ongoing building management coordination (waste, cleaning, access)

How to Keep Your Fitout on Schedule

Risks to Programme — and How to Mitigate Them

RiskMitigation
Slow client decisionsAssign a single decision-maker; set a 48-hour response expectation for design decisions
Planning permit delayStart the planning permit application as early as possible; engage a specialist planning consultant
Long-lead joinery not ordered early enoughPlace joinery order immediately on design sign-off, before permits are received
Landlord consent takes longer than expectedSubmit consent package as early as possible; engage with the landlord's team proactively
Trade availabilityBook subcontractors early; the best trades are booked 4–8 weeks ahead
IT contractor not coordinatedEngage IT contractor at design stage; give them the programme and require them to commit to key dates
Furniture lead time underestimatedConfirm furniture selection by Week 4–6; imported or custom furniture may have 14–20 week lead times
Variations (scope changes during construction)Freeze scope at design sign-off; all changes after this point generate variations with cost and time implications

The Variation Process

Variations are changes to the agreed scope during construction. They are unavoidable in most projects, but need to be managed tightly:

  • All variations must be documented in writing before works proceed
  • Each variation must include a cost and programme impact
  • You must formally approve the variation before the work is done
  • Verbal approvals ("just do it and add it to the bill") lead to disputes — always get it in writing

Frequently Asked Questions

Do I need to appoint a separate project manager for my fitout?

For most commercial fitouts under $2M, a quality design-and-build fitout builder provides sufficient project management. Appointing a separate owner's project manager (OPM) adds cost (typically 3–7% of project cost) but provides independent oversight. This is more commonly seen in large government fitouts, complex technical projects (hospitals, research facilities), or where the client organisation lacks internal fitout expertise.

How often should I visit the site during construction?

Attend the weekly site meeting (or fortnightly for smaller projects). Additional visits are welcome but co-ordinate with the site supervisor — site visits without notice can disrupt the workforce and raise safety obligations. The site supervisor should brief you on progress, any issues, and upcoming decisions at each meeting.

What is a defects list and how does it work?

At practical completion, you walk the fitout with the builder and document any items that are incomplete or not to specification. This list (called a defects list or snag list) is formally agreed and the builder commits to a completion date for each item. Items on the defects list do not prevent handover but must be rectified promptly — typically within 2–4 weeks of handover.

What happens if the builder falls behind programme?

First, identify the cause — is it a client-side delay (late decisions, late approval), a builder-side delay (trade unavailability, management failure), or an external cause (supply chain, council delay)? Builder-caused delays should be raised formally in the site meeting and tracked. If the builder is significantly behind and not recovering, engage your solicitor to review your contract rights. Most commercial fitout contracts include liquidated damages provisions for builder-caused delays.

Can I make changes to the design after construction has started?

Yes, but each change generates a variation — a formal cost and time assessment. Some changes are minor (paint colour, hardware selection) and have minimal impact. Others (moving a wall, relocating a kitchen) may require new drawings, revised permits, and significant construction rework. Freeze scope before construction starts whenever possible.

Spacez manages the complete project lifecycle — design, approvals, procurement, and construction — for commercial fitouts across Melbourne. Contact us to discuss your project.