Spacez insight · March 2026 · 8 min read
Office Fitout Timeline Melbourne: How Long Does It Really Take?
Planning an office fitout in Melbourne? Here's exactly how long each stage takes — from lease signing to moving in. Real timelines from Melbourne fitout…
Office Fitout Timeline Melbourne: How Long Does It Really Take?
Your lease is signed. Your team is growing. You've committed to a new office. Now the question every Melbourne business owner asks next:
How long is this going to take?
It's the right question to ask early — and the honest answer is: longer than you think, if you haven't planned properly.
A typical office fitout in Melbourne takes 10 to 16 weeks from design start to move-in day. But that number is almost meaningless without understanding what goes into each stage. A 400sqm Category B fitout in a Melbourne CBD tower has a very different programme to a 100sqm warm shell refurbishment in Cremorne.
This guide breaks down the real timeline — stage by stage — so you can plan your move-in date with confidence, not guesswork.
The Six Stages of an Office Fitout
Stage 1: Brief and Engagement (1–2 weeks)
Before a single line is drawn, your fitout company needs to understand your business: how many people, how you work, what's important, what you've learned from your current office, and what your budget is.
During this stage:
- Initial site inspection of the new tenancy
- Brief preparation: headcount, work modes, technology requirements
- Budget discussion: total project cost including design, construction, and fitout
- Signing of a design agreement or engagement letter
Don't skip this stage. A poorly defined brief causes design changes downstream, which cost time and money.
Typical duration: 1–2 weeks
Stage 2: Concept Design (2–3 weeks)
Your fitout company produces an initial floor plan layout and concept design showing:
- Floor plan with workstations, meeting rooms, breakout areas, and amenities
- Design direction: materials, colours, aesthetic approach
- Initial cost estimate based on the concept
At this stage you're reviewing and refining. Most clients go through one round of significant changes before a concept is approved.
For Melbourne CBD buildings: Your fitout company may also make an initial approach to building management at this stage to understand base building requirements and book in approval meetings.
Typical duration: 2–3 weeks
Stage 3: Design Development and Documentation (3–5 weeks)
Once the concept is approved, the project moves into full design development. This stage produces the documents that everything else is built from:
- Developed design drawings — detailed floor plans, elevations, reflected ceiling plans, joinery drawings
- Specifications — materials, finishes, fixtures and fittings schedules
- Mechanical and electrical design — HVAC zoning, lighting design, data and communications layout
- Structural drawings — if required for any structural changes
- Fire engineering — sometimes required in CBD high-rise buildings
This documentation is what goes to the building owner for approval, to the building certifier for the building permit, and to subcontractors for pricing.
Typical duration: 3–5 weeks (longer for larger or more complex fitouts)
Stage 4: Approvals (2–6 weeks — the most variable stage)
This is the stage where many fitout timelines blow out — not because of anything the fitout company does, but because approvals involve third parties who move at their own pace.
Building owner / landlord approval
Almost all commercial leases require the landlord to approve your fitout design before works commence. For institutional owners (listed property trusts, fund managers) this process can take 3–6 weeks. For private building owners it's typically 1–2 weeks.
Building permit
Most office fitouts in Melbourne require a building permit. Your fitout company appoints a building surveyor (private certifier) who reviews the design documentation and issues the permit. Typical building permit timeframe in Melbourne: 2–4 weeks.
These approvals can run in parallel — which is why a good fitout company submits to the building owner and building surveyor simultaneously.
For high-rise Melbourne CBD buildings: Fire engineering sign-off, base building services coordination, and building manager approval can add additional approval steps. Budget 4–6 weeks for approvals in CBD towers.
Typical duration: 2–6 weeks (run concurrently with final documentation where possible)
Stage 5: Construction (4–10 weeks)
Construction starts the moment the permit is issued and the site is available to access. For most Melbourne office fitouts, the construction programme looks like this:
Week 1–2: Demolition and structure
- Strip back existing fitout (if refurbishment)
- New partition framing
- Any structural works
Week 2–4: Services rough-in
- Mechanical ductwork and HVAC
- Electrical first fix (cable runs, conduit)
- Data and communications (cable runs)
- Plumbing (if any wet areas — kitchenettes, bathrooms)
- Sprinkler modifications (for Melbourne CBD high-rise buildings — this involves the building's base building contractor and adds coordination time)
Week 4–6: Lining and fitout
- Plasterboard to walls and ceilings
- Acoustic insulation
- Ceiling tiles or plasterboard ceilings
- Glazed partitions and door frames
Week 6–8: Fit-off and joinery
- Joinery installation (kitchen, reception, storage)
- Electrical second fix (switches, sockets, light fittings)
- Mechanical commissioning
- Flooring installation
- Painting
Week 8–10: Final finishes and defects
- Carpet laying
- Furniture delivery and installation
- Final painting and touch-ups
- Defects inspection and rectification
- Cleaning
- Practical completion
Typical construction duration:
- 100–200sqm office fitout: 4–6 weeks
- 200–500sqm office fitout: 6–8 weeks
- 500sqm+ office fitout: 8–12 weeks
Stage 6: Move-In and Defects Period (1–2 weeks)
Practical completion is when the fitout is finished to a standard where you can occupy and use the space. It's not necessarily when every single defect is rectified.
After practical completion:
- Your IT team commissions workstations, phones, and systems
- Furniture is installed (if not already done)
- Final cleaning
- You move in
The defects liability period (usually 12 months) then begins. Your fitout company rectifies any defects that emerge during normal use.
Typical duration: 1–2 weeks from practical completion to settled-in
Full Office Fitout Timeline Summary
| Stage | Duration |
|---|---|
| Brief and engagement | 1–2 weeks |
| Concept design | 2–3 weeks |
| Design development and documentation | 3–5 weeks |
| Approvals (landlord + building permit) | 2–6 weeks |
| Construction | 4–10 weeks |
| Move-in and commissioning | 1–2 weeks |
| Total | 13–28 weeks |
For a typical 200–400sqm CBD office fitout in Melbourne, budget 16–20 weeks from engaging a fitout company to moving in.
Why Melbourne Timelines Are Different
If you've searched "how long does an office fitout take" and found UK or US guides suggesting 6–8 weeks, those timelines don't account for what's involved in a Melbourne CBD office fitout.
High-rise building approval processes. Major Melbourne CBD towers — Bourke Street, Collins Street, Lonsdale Street, St Kilda Road — have institutional building owners with formal fitout approval processes. This adds 3–6 weeks that smaller buildings don't require.
Sprinkler modifications. If your new floor plan adds or moves meeting rooms, you'll likely need to modify the sprinkler system. In Melbourne CBD high-rise, this involves the base building's designated sprinkler contractor — coordinating their programme into your construction timeline adds time.
Building permit processing times. Melbourne's building permit processing through private certifiers typically takes 2–4 weeks. In busy periods, certifiers can be 1–2 weeks longer than expected.
Trade availability. Melbourne's construction sector is busy. Good subcontractors are booked ahead. If your fitout company is programming a project for 3 months from now, they need to book trades now. Leaving a project programme to the last minute costs time.
When Should You Start Planning Your Office Fitout?
If your lease commences on a specific date — or you have a hard move-in deadline — work backwards:
| Target move-in | Start engaging your fitout company |
|---|---|
| Tomorrow (emergency) | Too late for a quality outcome |
| In 2–3 months | Possible for small simple fitouts |
| In 4–5 months | Realistic for 200–400sqm standard fitout |
| In 6 months | Comfortable for complex CBD fitout |
| In 6+ months | Ideal — time for thorough design and good subcontractor pricing |
The most common mistake Melbourne businesses make is starting too late. A lease signed in January for a March commencement is 10 weeks — barely enough time to design and build a simple fitout, let alone a complex one.
If you're reading this article because your lease start date is 8 weeks away, call us. We'll be honest about what's achievable.
How to Keep Your Office Fitout on Programme
Engage early. The earlier you start, the more options you have. Late starts compress the programme and increase cost (overtime, premium trade rates).
Make decisions quickly. Fitout programmes stall when clients can't decide on finishes, furniture, or layout changes. Brief your decision-makers before the project starts and keep the approval chain short.
Freeze the design before construction. Design changes during construction are expensive and disrupt programme. Spend extra time in design development to get it right before the builder starts.
Choose a fitout company with their own trade relationships. Fitout companies that subcontract to regular, trusted trades get better availability and better accountability than companies managing a fresh tender process every project.
Build in contingency. Add 2 weeks to whatever programme you're given. Not because your fitout company is padding, but because approvals, deliveries, and inspections rarely run exactly to schedule.
Frequently Asked Questions
How long does a small office fitout take in Melbourne?
A small office fitout — 50–150sqm — typically takes 8–12 weeks from design start to move-in. Construction alone is 3–5 weeks. The approvals stage is the same regardless of size; that's where most of the time goes.
Can a Melbourne office fitout be done faster than 12 weeks?
Yes, in some circumstances. A warm shell fitout in a building with a private landlord, a simple design, and a fast building permit can be completed in 8–10 weeks. If your tenancy is already fitted from a previous tenant and you just need a refresh, 4–6 weeks is possible. We'll tell you what's realistic for your specific situation.
What causes office fitout delays in Melbourne?
The most common causes: late design decisions by the client, building permit delays, sprinkler modification lead times in CBD buildings, joinery manufacturing lead times, and late landlord approvals. We programme around all of these — the biggest variable is client decision-making speed.
Do I need to move out of my existing office during the fitout?
Not necessarily. If you're refurbishing your current tenancy, we can stage the works area by area while you remain in occupation. It's slower and more expensive than a vacant fitout, but it avoids the cost and disruption of a temporary office.
Does furniture come from the fitout company?
Furniture procurement is typically separate from the construction fitout, though some fitout companies manage it as a single package. We can manage furniture procurement for you or work alongside your furniture supplier — whichever suits your preference.
Plan Your Melbourne Office Fitout Today
Starting early is the single most important thing you can do to get a good outcome.
Our team works with Melbourne businesses at every stage — from lease negotiation (we'll look at the tenancy before you sign) to handover day. The earlier we're involved, the better the result.
Request a free consultation or learn more about our office fitout services in Melbourne.
Also useful: our commercial fitout cost guide — so you know what to budget before the design starts.
Spacez delivers office fitouts across Melbourne's CBD and inner suburbs: Collins Street, Bourke Street, St Kilda Road, Southbank, Cremorne, Richmond, Docklands, South Melbourne, and North Melbourne. We specialise in commercial fitouts exclusively — not residential, not retail on the side. Office fitouts are our core business.